CASE STUDY: INDUSTRIAL HVAC

At Silent-Aire we know that every location we provide Industrial HVAC solutions to has it's own unique challenges.

CASE STUDY: INDUSTRIAL HVAC

Facility: Potash Mine
Location: Saskatchewan, Canada
Engineering Designer: AMEC
Space serviced by AHU: Mill 1 Electrical Distribution Building (Cooling)

Challenges:

Manufacturing Industrial HVAC for a corrosive environment such as potash mine.

Solution:

Full 316L stainless steel construction inside and out to protect against site specific corrosion risks. Utilizes special epoxy coating on fans to reduce corrosion. Includes NEMA 4x enclosures for inside and outside wash-down.

amec2

CFM 26,000
Supply Fan 1 DWDI
Condenser Fans 2 DWDI
VFD Yes
DX Cooling Coil – R-134 Cu/Cu fin & tube
Electric Heating Coil Incoloy tube
Condenser Coil Cu/Cu fin & tube
DX Compressor & Accessories 2 @ Tandem Hermetic Scroll
Pre-Filter MERV 7
Final Filter MERV 13
Mixing Section Yes
Indoor/Outdoor Indoor
Wall Thickness 2”
Outer Casing 16 Ga. 316L Stainless Steel
Inner Casing 22 Ga. Solid and perforated 316L Stainless Steel
Fully Integrated Controls Yes
NEMA 4x Enclosures Yes
24 hr/day, 365 days/year continuous operation